Featured report / China project / Anhui
G529 Yeji railway-overpass sets first two 40 m box girders
Lu'an Municipal Transportation Bureau reported that the G529 Jinyue route Yeji section railway-overpass works set the first batch of two precast box girders above the operating Ningxi Railway during a two-hour railway work window on September 9, 2026. The source says the 408-meter bridge is the section's core control work and uses ten 40-meter precast box girders over the railway.