China project / Anhui
G529 Yeji railway-overpass sets first two 40 m box girders
Lu'an Municipal Transportation Bureau reported that the G529 Jinyue route Yeji section railway-overpass works set the first batch of two precast box girders above the operating Ningxi Railway during a two-hour railway work window on September 9, 2026. The source says the 408-meter bridge is the section's core control work and uses ten 40-meter precast box girders over the railway.
Key points
- The first railway-window operation set two precast box girders between 06:30 and 08:30 on September 9, 2026.
- The overpass span above the Ningxi Railway uses ten 40-meter precast box girders, each weighing about 180 tonnes.
- The source says the project had completed all 96 bored piles, 24 ground tie beams, 72 pier columns and 28 cap beams, while 62 precast box girders had been lifted across the wider works.
Source context
Source: Lu'an Municipal Transportation Bureau / Yeji District Transportation Bureau. Open the original publication for dates, figures and full context.
The Lu'an transport-bureau page includes construction photographs; PRECAST.WORLD does not reuse source media. The page is text-only.
View original sourceSource details
- Project: G529 Jinyue route Yeji section new-build works, Ningxi Railway overpass.
- Location named by the source: Yeji District, Lu'an, Anhui Province.
- Publisher date: September 10, 2026; event date: September 9, 2026.
- Publisher/source line: Yeji District Transportation Bureau on the Lu'an Municipal Transportation Bureau site.
Related technical reading
Connect this development with production methods and product requirements
The related article and product references cover production variables, plant interfaces, product scope and field records relevant to this development.
Need technical context for this signal?
Send the target market, product type, capacity plan or project context. PRECAST.WORLD can turn the signal into clearer technical notes.