Ghana project / Navuni Bridge
Ghana bridge project erects first prestressed-concrete T beams
China Railway Group reported on August 13, 2026 that the Ghana NB project completed erection of the first span of 40-meter prestressed-concrete T beams at Navuni Bridge on August 5 local time. The bridge uses five 40-meter simply supported spans, with 25 T beams planned across the full 200-meter bridge.

Key points
- The first-span lift covered five 40-meter T beams at Navuni Bridge.
- The bridge superstructure is described as 40-meter simply supported prestressed-concrete T beams.
- The bridge is 200 meters long and 12.5 meters wide, with 25 total T beams; each beam is 40 meters long and 127.32 tonnes.
Source context
Source: China Railway Group. Open the original publication for dates, figures and full context.
The original China Railway Group page includes project photographs; PRECAST.WORLD does not reuse source imagery and uses its own copyrighted scene illustration.
View original sourceSource details
- Project named by the source: Ghana NB project.
- Contractor named by the source: China Railway No. 5 Engineering Group under China Railway Group.
- Event date: August 5, 2026 local time; publisher date: August 13, 2026.
- Route context: 1.914 kilometers, tying the new bridge into existing roads at both ends.
Related technical reading
Connect this development with production methods and product requirements
The related article and product references cover production variables, plant interfaces, product scope and field records relevant to this development.
Need technical context for this signal?
Send the target market, product type, capacity plan or project context. PRECAST.WORLD can turn the signal into clearer technical notes.